PM Modi to Inaugurate Hadapsar, Baramati, Karad and Wathar Railway Stations in September Under Amrit Bharat Station Scheme
Reported By Amit Singh
Pune, 29th August 2025: Prime Minister Narendra Modi will inaugurate Hadapsar, Baramati, Karad and Wathar railway stations in September 2025 under the Amrit Bharat Station Scheme (ABSS).
The Amrit Bharat Station Scheme, launched by the Ministry of Railways in December 2022, aims at redeveloping 1,309 stations across India to transform them into modern, integrated transport hubs. Foundation stones for the redevelopment of these stations were laid in two phases on 6 August 2023 and 26 February 2024. The scheme emphasizes long-term development, multimodal integration, amenities for Divyangjans, sustainability, and future-ready infrastructure.
A total of 20 railway stations in Pune Division are covered under ABSS. Lonand and Kedgaon stations were inaugurated on 22 May 2025.
Hadapsar Railway Station
Budget: ₹24.86 crore
Scope of Work: Facade, portico, circulating area, COP and PF surface, seating facilities, toilet block, Divyangjan facilities, illumination, renovation, compound wall, second entry.
Completed: Building A, B, C, D (except sewer line)
In Progress: COP work 95%, platform surface 60%, FOB 40%, facade 40%, portico 35%, circulating area 10%, lift & escalator 18%, skywalk 20%, front road 15%
Yet to be Taken: Facilities, signage, illumination, seating
Baramati Railway Station
Budget: ₹11.40 crore
Scope of Work (Phase I): Facade, portico, circulating area, COP and PF surface, seating facilities, toilet block, Divyangjan facilities, illumination, renovation, compound wall, second entry, signage.
Overall Physical Progress: 87%
Completed: COP, septic tank, new toilet block, compound wall, new water booth
In Progress: Varanda with lobby 89%, waiting room toilet block 95%, portico 90%, platform surface (Kota stone fixing) 97%, circulating area 80%, main entrance gate 85%, booking office renovation 60%, booking office store extension 85%, electric office extension 85%
Yet to be Taken: Seating facilities, parking shed
Karad Railway Station
Budget: ₹12.51 crore
Scope of Work: Portico, circulating area, COP and PF surface, facade, seating facilities, toilet block, Divyangjan facilities, illumination, renovation, compound wall, second entry, signage.
Completed: PF-1 parking area compound wall, PF-1 upper class waiting room
In Progress: PF-1 portico 90%, PF-1 main entry 50%, parking area 90%, entrance lobby 80%, circulating area 80%, parking area compound wall 85%
Yet to be Taken: Divyangjan toilet, existing toilet work, landscape work, seating facilities, painting, illumination, signage
Wathar Railway Station
Budget: ₹7.97 crore
Scope of Work: Facade, portico, circulating area, COP and PF surface, seating facilities, toilet block, Divyangjan facilities, illumination, renovation, compound wall, second entry.
Completed: Union office dismantling 100%
In Progress: PF-1 portico 66%, main entry 45%, parking area 78%, entrance lobby 70%, circulating area 70%, parking area compound wall 60%, COP at PF-1 80%, platform surface 75%, waiting room toilet ACP 90%, water booth 60%
Yet to be Taken: Seating facilities, painting, illumination, signage